The £38M Birmingham City Council office development on Woodcock Street was completed in October 2011 and provides approximately 22000m<sup>2</sup> of accommodation over five floors for over 3000 employees.
 
The £38M Birmingham City Council office development on Woodcock Street was completed in October 2011 and provides approximately 22000m<sup>2</sup> of accommodation over five floors for over 3000 employees.
 
   
 
   
Birmingham City Council wanted the development to be a flagship project for both sustainability and collaborative working. Main contractor [http://www.thomasvale.com Thomas Vale] needed to balance this aspiration with a challenging timescale.  
+
Birmingham City Council wanted the development to be a flagship project for both sustainability and collaborative working. Main contractor Thomas Vale needed to balance this aspiration with a challenging timescale.  
  
 
A steel framed solution was the only option that allowed the team to meet the challenging time programme. The building’s floors were steel [[Steel_construction_products#Standard_open_sections|beams]] supporting 200mm thick [[Floor_systems#Precast_units|hollow core concrete planks]], left exposed to mobilise the [[Thermal_mass|thermal mass]]. As the majority of the beams supporting the floor planks were [[Steel_construction_products#Cellular_beams|cellular]] this eased the transfer of cool night air across the soffits. This negated the need for excessive mechanical cooling of the building via air conditioning, offering significant cost and carbon savings.  
 
A steel framed solution was the only option that allowed the team to meet the challenging time programme. The building’s floors were steel [[Steel_construction_products#Standard_open_sections|beams]] supporting 200mm thick [[Floor_systems#Precast_units|hollow core concrete planks]], left exposed to mobilise the [[Thermal_mass|thermal mass]]. As the majority of the beams supporting the floor planks were [[Steel_construction_products#Cellular_beams|cellular]] this eased the transfer of cool night air across the soffits. This negated the need for excessive mechanical cooling of the building via air conditioning, offering significant cost and carbon savings.  

Revision as of 16:31, 26 March 2019

Extract from an article in NSC September 2012

Debunking the Myth

               Woodcock Street 1.jpg
Image courtesy of Thomas Vale Construction
               Woodcock Street 2.jpg
Image courtesy of Thomas Vale Construction

The £38M Birmingham City Council office development on Woodcock Street was completed in October 2011 and provides approximately 22000m2 of accommodation over five floors for over 3000 employees.

Birmingham City Council wanted the development to be a flagship project for both sustainability and collaborative working. Main contractor Thomas Vale needed to balance this aspiration with a challenging timescale.

A steel framed solution was the only option that allowed the team to meet the challenging time programme. The building’s floors were steel beams supporting 200mm thick hollow core concrete planks, left exposed to mobilise the thermal mass. As the majority of the beams supporting the floor planks were cellular this eased the transfer of cool night air across the soffits. This negated the need for excessive mechanical cooling of the building via air conditioning, offering significant cost and carbon savings.

The BREEAM ‘Excellent’ rated building was delivered on time and on budget, while simultaneously achieving around a 31% reduction in operational CO2 emissions compared to the minimum standards required for Building Regulations Part L compliance.

Architect Associated Architects
Structural Engineer Scott Wilson
Main Contractor Thomas Vale Construction
Client Birmingham City Council