Difference between revisions of "Cheshire Police HQ, Blacon"

From SteelConstruction.info
 
(8 intermediate revisions by 2 users not shown)
Line 1: Line 1:
{{#image_template:image=File: Cheshire_Police_HQ.png|align=right|wrap=true|width=400}}
+
==Extract from an article in [https://www.newsteelconstruction.com/wp/wp-content/uploads/digi/2012pdf/1209NSCSepOct12.pdf#page=27 NSC September 2012]==
[http://www.mottmac.com Mott MacDonald] and [http://www.fairhurst.co.uk Fairhurst] were commissioned by Cheshire Police to design its new 2800m<sup>2</sup> headquarters in Blacon. Sustainability and energy efficiency were key objectives for this project along with cost and the need for a quick delivery.  
+
'''Debunking the Myth'''
 +
<br>
 +
{{#image_template:image=File:Cheshire_Police_HQ.png|align=right|wrap=true|width=400}}
 +
[https://www.mottmac.com/ Mott MacDonald] and [http://www.fairhurst.co.uk Fairhurst] were commissioned by Cheshire Police to design its new 2800m<sup>2</sup> headquarters in Blacon. Sustainability and energy efficiency were key objectives for this project along with cost and the need for a quick delivery.  
  
 
The team opted for a steel framed solution, rather than concrete, due to the relative cost and time savings the material offered. The steel framed building was designed to achieve [[Thermal_mass|thermal mass]], providing ‘inertia’ against temperature fluctuations.  
 
The team opted for a steel framed solution, rather than concrete, due to the relative cost and time savings the material offered. The steel framed building was designed to achieve [[Thermal_mass|thermal mass]], providing ‘inertia’ against temperature fluctuations.  
{{#image_template:image=File: Cheshire_Police_HQ_2.png|align=right|wrap=true|width=400}}
+
{{#image_template:image=File: Cheshire_Police_HQ_2.png|align=left|wrap=true|width=200}}
  
 
Edward Murphy, Mott MacDonald Technical Director says: ''[[Thermal_mass|Thermal mass]] can, if designed correctly, be just as effective within an exposed [[Floor_systems#Precast_units|precast floor]] with a steel frame as it can within a concrete frame. In this instance we chose to use steel with precast because of the cost and time efficiencies that it offered''.  
 
Edward Murphy, Mott MacDonald Technical Director says: ''[[Thermal_mass|Thermal mass]] can, if designed correctly, be just as effective within an exposed [[Floor_systems#Precast_units|precast floor]] with a steel frame as it can within a concrete frame. In this instance we chose to use steel with precast because of the cost and time efficiencies that it offered''.  
Line 9: Line 12:
 
As a result of using a steel frame to achieve [[Thermal_mass|thermal mass]], approximately 5% was saved on the cost over a concrete solution and the job was completed four weeks earlier than would otherwise have been expected.
 
As a result of using a steel frame to achieve [[Thermal_mass|thermal mass]], approximately 5% was saved on the cost over a concrete solution and the job was completed four weeks earlier than would otherwise have been expected.
 
{|class="wikitable"  width=400
 
{|class="wikitable"  width=400
|-
 
|'''Architect'''||
 
 
|-
 
|-
 
|'''Structural Engineer'''||Fairhurst
 
|'''Structural Engineer'''||Fairhurst
|-
 
|'''Steelwork Contractor'''||
 
 
|-
 
|-
 
|'''Main Contractor'''||Mott MacDonald
 
|'''Main Contractor'''||Mott MacDonald
Line 20: Line 19:
 
|'''Client'''||Cheshire Police
 
|'''Client'''||Cheshire Police
 
|}
 
|}
 +
 +
[[Category:Case studies - Thermal mass]]

Latest revision as of 09:34, 15 February 2021

Extract from an article in NSC September 2012

Debunking the Myth

               Cheshire Police HQ.png
               

Mott MacDonald and Fairhurst were commissioned by Cheshire Police to design its new 2800m2 headquarters in Blacon. Sustainability and energy efficiency were key objectives for this project along with cost and the need for a quick delivery.

The team opted for a steel framed solution, rather than concrete, due to the relative cost and time savings the material offered. The steel framed building was designed to achieve thermal mass, providing ‘inertia’ against temperature fluctuations.

               Cheshire Police HQ 2.png
               

Edward Murphy, Mott MacDonald Technical Director says: Thermal mass can, if designed correctly, be just as effective within an exposed precast floor with a steel frame as it can within a concrete frame. In this instance we chose to use steel with precast because of the cost and time efficiencies that it offered.

As a result of using a steel frame to achieve thermal mass, approximately 5% was saved on the cost over a concrete solution and the job was completed four weeks earlier than would otherwise have been expected.

Structural Engineer Fairhurst
Main Contractor Mott MacDonald
Client Cheshire Police