Thermal Mass in Buildings Webinar 2015 quiz

From SteelConstruction.info

Please answer the following 8 multiple choice questions, then click 'submit' to check the result. The pass mark for a CPD certificate is 6 out of 8, and you may retake the quiz as many times as you wish, but the questions will vary! Please note that one, two, three or all of the possible answers presented for each question may be right, and to gain a mark for that question all correct answers must be identified.

Good luck

Thermal Mass in Buildings

When casting an in-situ concrete floor, an aesthetically pleasing soffit may be required. Which of the following were identified as being necessary to ensure that this is achieved?

Formwork must be new and complete sections between designated construction joints must be capable of being concreted in a single operation
Formwork must be adequately supported to prevent differential movement
High standards of dimensional tolerance in casting the slabs is required and aesthetic surfaces must be protected after preparation to retain the specified surface finish.
All of the above

Which of the following statements is/are correct with respect to using permeable ceilings when utilising thermal mass?

An open area of 40% is about the maximum that can be used if a perforated ceiling is to hide the soffit.
Under test conditions, over 85% of the cooling effect of an exposed soffit can be obtained with a thin perforated steel ceiling.
When using a perforated steel ceiling, the loss in convective heat transfer is partly compensated by the action of the thin metal tiles absorbing and re-radiating heat from the air into the slab.
All of the above.

The quantity of mass in a building which can be linked to the internal atmosphere to provide thermal mass is governed by the ............ of the material of which the construction, usually the floor slab, is manufactured. What word is missing?

Linkage
Admittance
Absorption
Variation

Which of the following featured in the office/library case study in Seaham?

In parts of the building, acoustic suspended ceiling panels were installed to improve the acoustic environment.
A composite metal deck floor.
Water cooling in the floor slab.
All of the above

In the Aecom study, which, if any, of these floor systems provided the best thermal mass performance?

Composite metal deck slab
Reinforced concrete flat slab
Hollow core precast plank
They all provided the same performance

Which of the following statements is/are correct?

Used effectively, thermal mass will advance the time of peak temperature in a building.
Used effectively, thermal mass will delay the time of peak temperature in a building.
Used effectively, thermal mass will increased peak temperatures in a building
Used effectively, thermal mass will decrease peak temperatures in a building.

Both the Wessex Water building and the Cooperative HQ building utilised thermal mass. What was/were the common construction feature/features?

A composite metal deck floor
Beams support exposed precast concrete coffer units that sit on the bottom flanges of the beams.
Large atria allowing natural daylight to penetrate the floor plates.
All of the above.

Which of the following were identified as features of the case study for Shires House in Guiseley?

Long span construction.
A network of water pipes in the floor slabs to provide enhanced thermal capacity.
A composite metal deck floor.
All of the above